PFAS P2 Project Timeline

Project Timeline
Date Event
1 November 2020 Issued sampling contract.
January 2021 Issued Tech. Assistance RFP.
March 2021 Obtain Tech. Assistance Provider.
April 2021 Businesses to commit to project participation by signing MOU.
May 2021 Project kick-off meeting with group.
May 2021 Begin coordinating rounds of wastewater sampling. 
June 2021 Schedule site visit for source ID data collection.
June 2021 – December 2021 Periodic requests for data/information for source ID and further sampling.
August 2021 – September 2021 Group cohort meeting.
October 2021 – March 2022 Periodic requests for data/information for ID of P2 practices.
November 2021 – December 2021 Group cohort meeting.
February 2022 – March 2022 Group cohort meeting.
May 2022 – June 2022 Project closing - group cohort meeting.
June 2022 Report out to businesses with wastewater data, source identification results, and implementation recommendations.
June 2022 – September 2022 Amplify best practices by sharing findings.
By December 2022 Produce final report for EPA with case studies, project outputs, and outcomes.

 